Per-project risk tracking — severity, owner, mitigation, review cadence. The artifact that turns "what could go wrong" into a managed plan.
Open
Any editor can update. Vera routes questions to any team member with relevant expertise.
Owner: Mikkel Nygaard
You can read, edit and deprecate this skill.
Deep
Understands edge cases and can teach it.
Led
Has done it independently and owned outcomes.
A risk register is a living list of the things that could go wrong on a project, what we plan to do about each one, and who owns the watching. Every active project at Media Tech maintains one. The register lives in monday.com under the project's board, so it's visible to anyone with project access and is reviewed at the cadence the project's risk profile demands.
Risk management is not pessimism. It is the structured habit of asking "what would have to go wrong for this project to miss its goal?" while there is still time to do something about it. Risks that never become issues are a sign the system is working, not a sign the register was wasted effort.
A risk is a future event with non-trivial probability that, if it occurred, would prevent the project from meeting its goal — its scope, schedule, budget, or quality. A risk is not an issue (issues are already happening). A risk is not a dependency (dependencies are known relationships). A risk is not a list of fears (probability and impact must both be non-trivial).
If you can't answer "what specifically would need to happen for this to materialise?" the entry isn't a risk yet — it's a worry.
Every risk in the register has the following fields:
| Field | Example |
|---|---|
| ID | RISK-Castline-014 |
| Title | "OpenAI rate limit on AI Diary generation under launch-week load" |
| Description | Two-sentence specifics: the trigger, the consequence. |
| Likelihood | 1 (Rare) — 2 (Unlikely) — 3 (Possible) — 4 (Likely) — 5 (Almost certain) |
| Impact | 1 (Negligible) — 2 (Minor) — 3 (Moderate) — 4 (Major) — 5 (Severe) |
| Severity | Likelihood × Impact (1–25) |
| Owner | A single named individual. |
| Status | Open / Mitigating / Accepted / Closed |
| Mitigation | What we are doing to reduce likelihood or impact. |
| Contingency | What we will do if the risk materialises despite mitigation. |
| Review date | Next time this risk is re-evaluated. |
| Last updated | Date of the most recent change to any field. |
Review means actually looking at the entry, deciding whether likelihood or impact has changed, and updating the entry — not just scrolling past it.
A risk closes when one of three things happens:
Closed risks remain in the register for the life of the project as the historical record.
Active categories on the Castline risk register:
Each category should typically have 2–6 active risks at any time. Fewer suggests we're not looking; more suggests we're not closing.
Project Manager. The PM curates the register; each risk's owner is whoever has the most direct authority to act on the mitigation. Audited by the Master skill on a 30-day cadence.